Free Invoice Generator for Contractors: Labor, Materials & Progress Billing

A contractor invoice is not a freelancer invoice with a different job title. It has to survive being read alongside a contract, a schedule of values, a purchase order, and sometimes a lender's checklist — by a homeowner, a general contractor, or both. Get the structure right and it gets paid without questions. Lump everything into one line and it sits in someone's inbox awaiting clarification. And if you need the quote that comes before the invoice, our free contractor quote generator builds it in minutes with materials, labour, markup, and a PDF to send.

This guide covers what belongs on a contractor invoice, how progress billing and retainage actually work (with a fully worked example), how sales tax treats construction work, and how to build the whole thing with our free invoice generator — no sign-up, no watermark.

What makes a contractor invoice different

A standard service invoice lists what you did and what it costs. A contractor invoice must also answer: which job, under which contract, how far along is it, and how much of the contract has already been billed? The fields that carry those answers:

Progress billing, worked end to end

On a long job you don't invoice once at the end — you bill the value of the work finished since your last invoice, minus what you've already billed, less any retainage the contract holds back. The formula:

Amount due = (Contract sum × % complete) − Previously billed − Retainage held + Sales tax (if applicable) − Deposit applied

Here's a complete example — a bathroom remodel:

| Item | Calculation | Amount | |---|---|---| | Original contract | | $45,000 | | Approved change order (CO 1: upgraded tile) | | $3,000 | | Contract sum | $45,000 + $3,000 | $48,000 | | Completed to date (50% complete) | 50% × $48,000 | $24,000 | | Previously billed (draw 1) | | − $9,600 | | This invoice (work billed now) | $24,000 − $9,600 | $14,400 | | Retainage held (10%) | 10% × $14,400 | − $1,440 | | Sales tax | None — see below | $0 | | Amount due | $14,400 − $1,440 | $12,960 |

Note the order of operations: retainage is calculated on this invoice's amount, not on the whole contract, and the change order raises the contract sum before any percentage is taken — so your percent complete is always measured against the new total. On the final invoice, you bill the last of the contract and ask for every retained amount back. Keep one invoice per stage and you have the full payment history of the job in order.

A free generator handles this if you map the fields deliberately: put the draw number ("Progress billing 2 of 4") and the retainage breakdown in the notes field, list labor and materials as separate lines, and record retainage as a deduction so the total reconciles. If your generator has a discount field, that is the usual place to subtract retainage visibly. For the milestone structure behind the draws — deposit, progress invoices, final invoice — see our milestone billing guide.

Sales tax: the rule most contractors get wrong

In many US states, a contractor who builds or improves real property is treated as the consumer of the materials: you pay sales tax when you buy them, and you do not add sales tax to the client's bill. That's why the worked example above shows $0 tax. But the treatment turns on your state and on how the contract is written:

Other states use their own rules, and some tax repairs differently from new work. The safe move: confirm the treatment with your state revenue department (or your accountant) before you set the tax field, and never copy another trade's invoice as your tax authority. Our generator lets you set any tax rate with your own label — or leave tax off entirely — so it fits either treatment.

Change orders: bill them separately, always

Never fold extra work into an existing line — it reads as a price increase, and it is the most common reason a construction invoice gets short-paid. Instead:

  1. Number each one — CO 1, CO 2, matching the signed change order form.
  2. Describe and price it in the client's words — say what changed and the agreed price, keeping the wording identical to the signed form.
  3. Add it to the contract sum — approved changes raise the total your percentages are measured against.
  4. Bill only after approval — if the change was verbal, get written confirmation before it appears on an invoice.
  5. Treat removed work as a credit — agree the credit in writing first, then lower the original line or show the reduction visibly so the bill still reconciles.

If you're billing against a purchase order rather than a contract, our guide to invoicing against a purchase order covers the PO-number and approval-chain details.

Three mistakes that delay payment

Lumping labor and materials. One combined figure makes tax treatment impossible to verify and slows approval on both the homeowner and GC side. Separate lines cost you nothing and remove the most common question.

No PO on subcontractor bills. A GC's system often cannot route an invoice without the purchase order number. Sending your invoice early in their billing cycle, with the PO visible, is frequently worth more than shortening your payment terms.

Undocumented extras. Extra work with no change order reference is the single most common reason a construction invoice is short-paid. If it isn't on a signed change order, it doesn't belong on the invoice yet.

Protect your lien rights

Mechanics lien rules are state-specific and deadline-driven, and they usually run from the date work was performed or materials supplied — not from the date you invoiced. Keep dated invoices, delivery tickets, and receipts together for every job, and note on the invoice that lien rights are reserved until payment is received in full. This is general information, not legal advice: lien deadlines are short and unforgiving, so check your state's rules or talk to a construction attorney before you rely on them.

Build it in two minutes

Our free invoice generator covers the contractor structure without an account: separate line items for labor, materials, permits, and equipment; a notes field for the draw number, retainage breakdown, and lien-rights note; a tax field you set to your state's treatment (or leave off); and a clean PDF with no watermark. Start from a quote for the job, then convert the same structure into the invoice — the quote-to-invoice handoff is where most billing errors creep in, and keeping the line items identical removes them.

Frequently asked questions

Should labor and materials be on separate lines?

Yes. Many states tax materials differently from labor, and general contractors and homeowners both expect to see the split. Separate lines also make change orders easier to justify and let the client verify where the money went.

Can I use a free generator for progress billing?

Yes, with deliberate field mapping: note the draw number ("Progress billing 2 of 4") and the retainage breakdown in the notes field, bill only the completed portion of each line, and subtract retainage visibly as a deduction. You won't get automatic schedule-of-values tracking — that needs paid software — but the invoice itself will reconcile.

Do I need my license number on the invoice?

Several states require a contractor license number on contracts and billing documents. Add it to your business details block; it also reassures homeowners that they're dealing with a licensed trade.

Do contractors charge sales tax on invoices?

Often no: in many states the contractor is the consumer of the materials and pays tax at purchase, billing the client none. But it depends on the state and the contract type — Florida's retail-sale-plus-installation contracts are a notable exception. Confirm with your state revenue department before setting the tax field.

What payment terms work for contractor invoices?

Agree them before the project starts and print them on every invoice. Small jobs are usually billed as soon as they're finished; longer projects at agreed milestones or monthly. Net 30 is standard for commercial clients and developers; Net 10 or Net 15 fits homeowner progress invoices. For the general framework, see how to write an invoice.

Is there a limit on how many line items I can add?

No. Add as many labor, material, permit, and equipment lines as the job needs — the totals and tax recalculate automatically.